SUBSCRIBE

e-Newsletter

Get updates and information by email with our FREE e-Newsletter

Facebook
Connect with us on Facebook!

News & Events

Nutt Road Project Update

Posted on Sep 15, 2017

Nutt Road Project Update

November 9 -


This 200-foot segment has had the old road removed and is “based in” with underdrain and  geofabric installed.

This segment has curb installed and material has been placed, but not compacted, in preparation for sidewalk.

This segment now has curb and a compacted base behind the curb in preparation for future sidewalk.

October 25 -

 

  • Curb has been placed on the south side of Nutt Road between Cherry Tree Terrace and Beaufort Run and on the north side from 2211 to 2151.
  • Traffic from Beaufort Run is now required to exit and enter from the east, toward Clyo Road.
  • Approximately 200 feet of water main has been installed, with 500 more feet planned for this part of the project.
  • Storm sewer currently is being placed from the creek at 2021 Nutt to 2151 Nutt.
  • The contractor expects to begin placing curb in this section in early November and will then place
    Upper Left: Manhole for storm sewer set in place. Upper Right: Catch basin at Beaufort Run. Above: Trench with a 24-inch TransCanada gas pipe exposed. A new water main will be placed beneath the pipe.
    asphalt in the widened areas tomake the road passable for the winter months.
  • ATT has lowered several conduits at 2021 which would have interfered with placement of curb and sidewalk. DPL has changed electric service to 2021 to facilitate ATT’s work.

September 25 -

Crews are working west of Cherry Tree Terrace. The installation of underdrain is currently underway and back filled with gravel. Crews anticipate setting up to pour curbing toward the end of the month.

 

 

September 15 -

Sidewalk installation was completed September 14 on Nutt Road bewteen Clyo Road and Cherry Creek Terrace.

Starting Wednesday, September 20, the traffic detour will change so that crews can begin installing and replacing curbing between Cherry Creek Terrace and Beaufort Run. Residents exiting onto Nutt Road from Cherry Creek must turn right (east) toward Clyo.

Traffic turning onto Nutt Road from Beaufort will continue to turn west.

PICTURED -
Right:
Sidewalk, looking from Clyo Road
Bottom Right: Construction at Cherry Tree Terrace and Nutt Road
Bottom Left: Contractor working on Nutt Road, with Clyo Road in the background


_____________________________

August 29 -

On August 28, contractors were able to place the base course of asphalt on Nutt Road, between Clyo Road and Cherry Tree Terrace. This photo was taken about midway between Clyo and Cherry Tree, looking toward the west.

_________________________

August 16 -

During the past week, curb has been placed between Clyo Road and Cherry Tree Terrace.

Next week, the plan is for sidewalk to be installed along the south side of Nutt between Clyo Road and Cherry Tree Terrace.

The contractor anticipates that pavement will be placed the week of August 28 between Clyo Road and Cherry Tree Terrace.

August 3 -

Nutt Road's base layer has been excavated and built up with compacted stone and underdrain.

June 19 -

Starting June 19, Nutt Road will be closed for 90 days from Clyo Road at the east end to just west of Beaufort Run. Access will be maintained for local residents and service providers.

Project Overview

The project includes widening Nutt to three lanes between School House Park and Clyo Road (with the exception of a small section near 2021 Nutt Rd. where a 24-inch gas pipeline crosses).

Improvements along the entire one-mile section include curb and gutter, plus a sidewalk along the south side of the road. The estimated $3.1 million project is funded by Washington Township.

This marks the third and final phase of Nutt Road widening and improvements which began in 1996 when a 4,800-foot section was widened from State Route 48 to Quailwood Trail. Phase two, a 2,100-foot stretch from Quailwood to west of School House Park, was completed in 2010.

 

Calendar of Events



SMTWTFS
 1234
567891011
12131415161718
19202122232425
2627282930 

What's Happening Soon?

  • Washington Township Trustee Meeting

    December 4, 2017 - Read More

  • Washington Township Trustee Meeting

    December 18, 2017 - Read More

  • Contact Us

  • We're Hiring

  • FAQ